Plant assembly

Un dessin très détaillé et coloré généré par ordinateur du Complexe tokamak d'ITER et des 15 principaux systèmes qui doivent y être installés pour le bon fonctionnement de la machine ITER. Un peu d'explanation de l'assemblage des systèmes.

Everything outside of the Tokamak boundary falls into the category of "plant assembly"—including the installation of equipment and systems inside of the Tokamak Complex (pictured) as well as the more standard plant installation works in buildings across the ITER platform.
 

A very detailed and colorful computer-generated drawing of the 15 major ITER plant systems that will help the machine operate.

First-phase plant assembly contracts cover the systems needed for the Start of Research Operations. This category includes the cryogenic, cooling water and electrical plants; basic diagnostics; some radio frequency heating, as well as large captive components that must be installed in the buildings early.
 

For the most complex and time-sensitive area—the Tokamak Complex—the choice has been made to split the works between two contractors, and to organize the division of scope by system, location and sequence (see detail below). Although the two assembly contractors for the Tokamak Complex work in distinct areas, their work scope contains many common elements.
 

Mechanical and piping works: vessels, piping systems, heat exchangers, pumps, motors; cable trays and cable pulling; wave guides; piping thermal installation; pressure tests, flushing. Electrical, instrumentation and control: DC busbars, switching equipment, power cables, I&C cables and cabinets.
 

The installation of equipment is progressing in the Tokamak Complex. Work to install systems is also underway in plant buildings across the ITER platform; others have been fully equipped and turned over to the ITER Organization for commissioning.
 

5

km cryolines

5000

km cables

40

km cooling water piping

170

local control systems

Contractors carrying out the day-to-day work under the oversight of the ITER Organization:

TCC/1

Tokamak Complex Contract 1: Fincantieri Consortium (Fincantieri S.p.A., Fincantieri SI S.p.A., Delta-ti Impianti S.p.A., Comes S.p.A.) For the installation of heating and current drive, diagnostics, fuelling, secondary cooling, and vacuum components. 
 

TCC/2

Tokamak Complex Contract 2: META SNC (Ponticelli Freres SAS, Cobra Instalaciones y Servicios SA, and Empresarios Agrupados Internacional SA.) For the installation of primary machine cooling water, test blanket module equipment, some vacuum pipework, vacuum vessel pressure suppression.
 

BALANCE OF PLANT

Work on the platform has been divided into these contracts: Group 1 - equipment installation in the Magnet Power Conversion buildings; Group 2 - installation of cooling water plant; Group 3 - electrical distribution; Group 4 - installation of multi-process lines; Group 5 - installation of DC busbars, switching networks and fast discharge units; Group 6 - installation of converters, transformers, reactive power compensation units, and harmonic filters.