Components

The fine art of preservation

To keep components and materials in good condition prior to entering service, a set of actions needs to be performed. These activities, which are specific to a given piece of equipment, are collectively referred to as "preservation activities."

Image1_ed.jpg
Preservation is particularly critical for "captive" components that may need preserving for a decade or longer before entering service. Here, a worker performs a white cloth test to check for moisture on a cryostat support bearing during a preservation inspection.
At ITER, equipment passes through three preservation stages from delivery to commissioning. Stage one, under the responsibility of Integrated Logistics Management (ILM), begins when a component arrives on site and is placed in storage. Stage two begins when equipment is issued from storage and put in the care of the works contractor for installation. Stage three covers the period after installation, but prior to commissioning. During this third stage, responsibilities typically fall under the general services contractor or a maintenance contractor.

A small central preservation team coordinates the preservation activities and tracks the equipment over the three stages, "We liaise with the responsible parties during each of the stages to make sure the equipment has clearly defined preservation requirements, and a responsible party is assigned to perform the activities," says Richard Brown, Maintenance Management Officer in the Operations Division. "We also make sure the activities are planned and scheduled, and that any issues that are uncovered are recorded and followed up."

Preserving captive components

Preservation is particularly critical for "captive" components that may need preserving for a decade or longer before entering service. A captive component is typically a large item that, once installed, can no longer be easily removed. It is closed in either by a building structure or by other large equipment. Examples of captive equipment are the cryostat support bearings (CSBs) and the four large tanks in the drain tank room.

The 18 bearings, each about the size of a dining room table, are installed in the Tokamak pit. These bearings allow some relative movement in the cryostat to buffer expansion due to temperature changes, or excessive loads that hit the vacuum vessel in the cryostat. The preservation activities include regularly monitoring the air humidity conditions in the Tokamak pit and performing visual checks for signs of grease, moisture or other aggressors.

Pat_Image 2.jpg
Recording preservation activities using the SPMat Mobile Companion software.
Preservation activities for the four large stainless-steel tanks include performing visual inspections to check for any signs of corrosion, and to ensure that the tanks are protected from any co-activities that could result in cross-contamination. For example, particular care needs to be taken to ensure that the stainless-steel tanks are not contaminated by dust from other forms of steel—a real risk when somebody is cutting or working with carbon steel as part of construction activities in the area.

Tracking all preservation activities

"Some of the activities may seem rather simple," says Brown. "They are nevertheless critical to ensuring the equipment is retained in good condition, and to reducing the risk of problems occurring when the system is commissioned. For example, motors and pumps need to be turned regularly to avoid brinelling (the permanent indentation of a hard surface) of the bearings, valves have to be greased and operated to avoid seizure, and vessels need to be kept inerted (filled with inert gas to keep air from coming in and moisture from developing) to prevent corrosion. The challenge is to keep track of all activities and ensure the responsibility for executing them is clear at all stages."

Over time, preservation will become more challenging. More first-of-a-kind equipment will be installed as assembly and construction progresses. This means that both the volume, but also the complexity of preservation activities, will increase substantially.

"In addition to managing the preservation activities associated with conventional plant equipment, we will also have some preservation requirements that are quite specific to ITER systems," says Brown. "For example, the gyrotrons used in the electron cyclotron heating system must have the quality of the vacuum maintained during long term storage. This means the internal ion pump must remain connected to a high voltage power supply. For cases like this we have to make sure that the correct provisions are in place before the items are received on site."

To stay on top of all activities, the preservation team helped define a process that starts before equipment is delivered on site. Before delivery, the technical responsible officer (TRO) ensures that the preservation requirements are defined and available. Usually, these are based on the original manufacturer's recommendations, but in cases where nothing is prescribed by the manufacturer, the TRO relies on standard guidelines for the type of equipment to write the preservation requirements.

Drain_Tank_Weld_2_small.jpg
The four large stainless-steel tanks, located at the lowest basement level (B2) of the Tokamak Complex, are among the components that require preserving.
"The preservation team ensures that the requirements are clearly communicated to whoever is responsible for performing the activities, and that any findings from the activities are reported," says Brown. "Last year we began using a set of key performance indicators to help monitor progress and help everyone to understand what parts of the process we need to improve."

New software provides real-time reporting and information sharing

To help improve the overall implementation of the process, ITER is rolling out a new piece of web-based software called SPMat Mobile Companion, which will allow real-time reporting on preservation activities in the field. The software runs on any tablet or handheld device to allow technicians to record the activities directly.

The new system will also allow TROs to get more up-to-date reports on the preservation activities carried out on their equipment. The software includes a workflow engine that allows people to schedule tasks, define to-do lists and receive alerts to stay on top of activities. The new system provides better traceability and auditability, especially for safety-critical, protection-important components.

"We went live with the new software in May," says Brown. "We are steadily expanding the scope of the equipment managed in the new tool, and we are training users. The new software makes it easier for people in the field to perform preservation activities, and it provides more detailed and up-to date information for equipment owners."