Image of the week
E-house finds a home
26 Nov 2018
In February 2017, two very cumbersome loads were delivered from China to the ITER site: measuring respectively 8.3 and 8.7 metres in width, the two "E-houses" for the steady-state electrical network came close to reaching the maximum 9-metre gauge of the ITER itinerary.
On the day following the delivery, the slimmer of the two was installed in its final home between the electrical switchyard and the row of electrical transformers, while its near twin was settled into storage at the entrance of the ITER site. On 22 November, this second E-house was transported to its platform location and installed.
Once fully equipped, E-houses accommodate dozens of instrumentation and control cubicles that relay orders from the control room to the installation's high voltage components.