Subscribe options

Select your newsletters:

Please enter your email address:

@

Your email address will only be used for the purpose of sending you the ITER Organization publication(s) that you have requested. ITER Organization will not transfer your email address or other personal data to any other party or use it for commercial purposes.

If you change your mind, you can easily unsubscribe by clicking the unsubscribe option at the bottom of an email you've received from ITER Organization.

For more information, see our Privacy policy.

News & Media

Latest ITER Newsline

  • Poloidal field magnets | The last ring

    As the massive ring-shaped coil inched its way from the Poloidal Field Coils Winding Facility, where it was manufactured, to the storage facility nearby where i [...]

    Read more

  • Heat rejection | White "smoke" brings good news

    Like a plume of white smoke rising from a cardinals' conclave to announce the election of a new pope, the tenuous vapour coming from one of the ITER cooling cel [...]

    Read more

  • WEC 2024 | Energy on centre stage

    The global players in the energy sector convened in Rotterdam last week for the 26th edition of the World Energy Congress (WEC). The venue was well chosen, wit [...]

    Read more

  • Fusion world | The EU blueprint for fusion energy

    The EU Blueprint for Fusion Energy workshop, convened by the European Commission's Directorate-General for Energy, brought together key stakeholders in the fiel [...]

    Read more

  • Neutral beam injection | ELISE achieves target values for ITER

    Researchers at the Max Planck Institute for Plasma Physics in Garching, Germany, have generated the ion current densities required for ITER neutral beam injecti [...]

    Read more

Of Interest

See archived entries

ITER assembly

Last major assembly contract signed

One year after finalizing two major machine assembly contracts, the ITER Organization has chosen the contractors who will carry out assembly and installation activities inside of the Tokamak Complex.

Co-activity in the Tokamak Complex will be a challenge to manage, as ITER Organization assembly contractors work inside of congested areas alongside the European Domestic Agency contractors who are finishing the installation of building services such as HVAC, fire protection and electrical services. Also challenging are the installation tolerances, the large number of components and the tight schedule. (Click to view larger version...)
Co-activity in the Tokamak Complex will be a challenge to manage, as ITER Organization assembly contractors work inside of congested areas alongside the European Domestic Agency contractors who are finishing the installation of building services such as HVAC, fire protection and electrical services. Also challenging are the installation tolerances, the large number of components and the tight schedule.


Following competitive global tender campaigns managed by ITER's Procurement & Contracts Division, two international groups—one incorporated as a consortium and the other as a commercial partnership—have been awarded contracts for installation activities inside of the Tokamak Complex.

These phased, long-term contracts will cover the pre-assembly and installation of the millions of components that make up the plant systems supporting the ITER machine, including fuelling, vacuum, diagnostics, cooling, power, and heating. The two assembly contractors for the Tokamak Complex will carry out similar types of installation tasks, notably mechanical and piping works (vessels, piping systems, heat exchangers, pumps, motors; cable trays and cable pulling; wave guides; piping thermal installation; pressure tests), and electrical- and instrumentation-and-control-related works (DC busbars, switching equipment, power cables, I&C cables and cabinets). 

  • The TCC1 assembly contract—for the installation of heating and current drive, diagnostics, fuelling, secondary cooling, and vacuum components—was signed in December 2019 by the ITER Organization and the Fincantieri Consortium (Fincantieri S.p.A., Fincantieri SI S.p.A., Delta-ti Impianti S.p.A., Comes S.p.A.)
  • The TCC2 assembly contract—for the installation of primary machine cooling water, test blanket module equipment, some vacuum pipework, vacuum vessel pressure suppression—was signed in December 2020 by the ITER Organization and the META SNC (Ponticelli Freres SAS, Cobra Instalaciones y Servicios SA, and Empresarios Agrupados Internacional SA.).
These contracts are the last major assembly and installation contracts planned for first-phase ITER assembly. (Two major contracts for Tokamak assembly, as well as five "balance of plant" contracts are already underway.)  

"The Procurement & Contracts teams have worked in very close collaboration with the Legal, Finance, Project Control, Quality and Nuclear Safety teams to prepare, develop, select and negotiate the two Tokamak Complex contracts. The two partners were chosen based on excellent technical capability at a competitive price, and we now need to collectively deliver on these promises through a deep collaboration between the teams at all levels. Such effective collaboration doesn't happen overnight; it requires a common sense of purpose that's aligned with the long-term business interests of all the companies involved," commented Christophe Dorschner, head of Procurement & Contracts Division at ITER.

Within the ITER Organization, the contracts are managed by Machine Assembly Planning & Contract Management Section (part of the Machine Construction Department) in close collaboration with Tokamak Complex Division.

Each contract is broken into phases, with detailed works assigned progressively to the contractors through ITER Organization work packages. The execution of assembly works will take place under the overall responsibility of the ITER Construction team and the day-to-day management of ITER's Construction Management-as-Agent, MOMENTUM.

Although the works will be concentrated in the Tokamak Complex (outside of the Tokamak machine boundary), some activity will also take place under these contracts in the Radiofrequency Building and Assembly Hall. Part of the expected challenge will be the coordination on the ground between Tokamak Complex contractors, contractors to the European Domestic Agency who continue to progress the installation of building services, and other dedicated teams carrying out the installation of multi-process cryolines, busbars and magnet feeders.

For more information on the ITER strategy for machine and plant assembly, see this article.