First plasma: 2025
To determine the precise date of ITER's First Plasma, hundreds of engineers, technicians and schedulers worked for nearly 18 months to reconcile the latest information from manufacturers in over twenty countries with construction progress on site. A number of variables were also taken into account—such as how much time could be gained by hiring more specialists or increasing the budget. The result? An updated calendar and a new date for First Plasma: December 2025.
In offices and factories on three continents, ITER teams are fully aligned with this new schedule, which the ITER Council has validated as "challenging but technically achievable." Weekly and monthly tracking of the key milestones is carried out to monitor adherence to the schedule and act quickly in the case of any slippage.
Thus, in November 2025 the first "small star" will be created inside of the ITER Tokamak—exactly 40 years after a vast international initiative in fusion was set in motion by world leaders Gorbachev and Reagan at the Geneva Superpower Summit in November 1985.
The long gestation period of the ITER Project can be explained in part by the challenges of creating an international organization from scratch, the complexity of its organization and governance (7 Members, 35 countries), and finally the huge scientific, technological and financial challenges of the program.
But all of the incremental steps that must be achieved are now drawn out through to the machine's First Plasma—a milestone in itself, but also the beginning of an experimental campaign that will last at least 20 years.
Beyond its symbolic importance, ITER's First Plasma will also be an important trial run for the machine—the first occasion to verify the correct alignment of the machine's magnetic fields and the correct functioning of key systems (electrical supply, cryostat, cooling water, cryogenics, etc.).
The very first low-power hydrogen plasma—lasting only a few milliseconds—will be followed by other "shots" of increasing power and duration. This shakedown mode, lasting a few weeks, will be followed by a shutdown phase during which the systems that are indispensable for hydrogen and helium plasmas at nominal power are installed. The first production of fusion power will take place during the machine's nuclear phase, scheduled for the middle of the following decade.