On 27 August, a gathering takes place in the Tokamak Pit to celebrate the completion of the "Final Pour." The finalization of the Tokamak Complex basemat (15 segments, 14,000 m³ of concrete, 3,600 tonnes of rebar) required eight months. Hundreds of people contributed to the different aspects of its realization, including design, procurement, scheduling, quality, finance and construction.