  • Vacuum vessel repair | A portfolio

    Whether standing vertically in the Assembly Hall or lying horizontally in the former Cryostat Workshop now assigned to component repair operations, the non-conf [...]

    Read more

  • European Physical Society | ITER presents its new plans

    The new ITER baseline and its associated research plan were presented last week at the 50th annual conference of the European Physical Society Plasma Physics Di [...]

    Read more

  • Image of the week | The platform's quasi-final appearance

    Since preparation work began in 2007 on the stretch of land that was to host the 42-hectare ITER platform, regular photographic surveys have been organized to d [...]

    Read more

  • Cryopumps | Preparing for the cold tests

    Before being delivered to ITER, the torus and cryostat cryopumps are submitted to a  comprehensive series of factory acceptance tests. This is not sufficie [...]

    Read more

  • Fusion technologies | Closing a fusion schism

    Historically, inertial confinement and magnetic confinement approaches to fusion have been parallel, separate processes. The ITER Private Sector Fusion Workshop [...]

    Read more

Of Interest

See archived entries

Busbar installation

"Power cords" thicker than train rails

Connecting an electrical device to a power source requires an extension cord, generally made of stranded copper wire. Depending on the required current intensity—are you plugging in a bedside lamp, a washing machine or an arc welder?—the cord's section ranges from a few millimetres to more than one centimetre. In the ITER magnet system, where huge components need to be fed with intense DC current, the equivalent of the electrical cord is a "busbar." The largest ITER busbars are thicker than a train rail and can carry current 7,000 times more intense than a heavy-duty electrical cable.

A busbar is to an ITER magnet what an extension cord is to a bedside lamp—a way to connect an electrical device to a power source. In ITER, the largest busbars are thicker than a train rail and can carry current 7,000 times more intense than a heavy-duty electrical cable. (Click to view larger version...)
A busbar is to an ITER magnet what an extension cord is to a bedside lamp—a way to connect an electrical device to a power source. In ITER, the largest busbars are thicker than a train rail and can carry current 7,000 times more intense than a heavy-duty electrical cable.
Busbars are steel-jacketed aluminium bars actively cooled by a constant flow of pressurized water. There will be close to five kilometres of DC busbars—amounting to 500 tonnes of material—in the ITER installation, all procured by Russia.

The busbar network originates in the twin Magnet Power Conversion buildings, where AC current from the grid is converted  into DC current suitable for the magnet system. The canary-yellow-lacquered bars exit the buildings through "mezzanines" and pass over two 50-metre-long bridges to the Tokamak Building, where they snake under the ceiling to reach their hungry "clients": the machine's 18 toroidal field coils, 6 poloidal field coils, 18 correction coils and 6 central solenoid modules, plus the switching network unit for the initial plasma boost and the fast discharge unit that will deal with possible quench events.

In the twin Magnet Power Conversion buildings, the installation of approximatively 1.25 kilometres of busbars is almost complete. The focus now is on the Diagnostics Building's basement level (B2) where teams are busy bolting busbars to their supports anchored in the ceiling.

Busbars at the basement level are for all 18 toroidal field coils, which are connected in series, poloidal field coils # 4, 5 and 6, the three lower modules of the central solenoid and a set of side and bottom correction coils.

Once bolted to their supports, the long (up to 12 metres) and heavy (up to 4 tonnes) busbar lengths must be connected to one another and to cooling water collectors, and hose connections must be installed before the whole system can be tested and commissioned. (Click to view larger version...)
Once bolted to their supports, the long (up to 12 metres) and heavy (up to 4 tonnes) busbar lengths must be connected to one another and to cooling water collectors, and hose connections must be installed before the whole system can be tested and commissioned.
In an environment already crowded with cable trays and all sorts of piping and HVAC ducts, the task is particularly challenging: individual busbar segments are sometimes very long (up to 12 metres) and quite heavy, ranging from 2 to 4 tonnes in weight.

Moving and adjusting the beams into position is a delicate operation that requires the coordinated movements of forklifts and pulley systems before they can be manually bolted to their support.

Once in place, the busbars need to be connected to one another and to cooling water collectors, and hose connections must be installed before the whole system can be tested and commissioned using dummy coils.

Busbar installation in the Diagnostics Building began a little more than two weeks ago and is now approximately 20 percent complete. In 2021, similar operations will be performed at the third floor of the Tokamak Building (L3) to connect another set of poloidal field coils, central solenoid modules and correction coils.
 