Subscribe options

Select your newsletters:

Please enter your email address:

@

Your email address will only be used for the purpose of sending you the ITER Organization publication(s) that you have requested. ITER Organization will not transfer your email address or other personal data to any other party or use it for commercial purposes.

If you change your mind, you can easily unsubscribe by clicking the unsubscribe option at the bottom of an email you've received from ITER Organization.

For more information, see our Privacy policy.

News & Media

Latest ITER Newsline

  • Tokamaks | Different approaches around the world

    Look east, look west ... tokamak projects are underway in different parts of the world. All of them are benefiting from and complementing the pioneering work al [...]

    Read more

  • Construction site | A guide to work underway

    Just like the ITER worksite, drone photography is also making progress. This view of the ITER platform is the sharpest and most detailed of all those we have pu [...]

    Read more

Of Interest

See archived entries

Sub-assembly tools

A 12-tonne beam, a crane and a little push

There is nothing remarkable about lifting a 12-tonne beam. Except when it happens in the spectacular setting of the ITER Assembly Hall, and the beam needs to be fitted with extreme precision into a structure as monumental as the ITER sector sub-assembly tools.

The first 12-tonne beam is slowly lifted 22 metres above ground. (Click to view larger version...)
The first 12-tonne beam is slowly lifted 22 metres above ground.
Towering 22 metres above ground, the vacuum vessel sector sub-assembly tools (SSATs) are formidable handling machines that will be used to pre-assemble vacuum vessel sectors with a pair of toroidal field coils and thermal shield segments before integration in the machine.

The assembly of SSAT-1 began in November 2017 and is now complete. Work on its identical twin SSAT-2 started in September the following year and is now entering its final phase.

Positioned on both sides of the beam, CNIM specialists precisely align the suspended beam and the massive supporting pillars—an operation that can only be performed manually. (Click to view larger version...)
Positioned on both sides of the beam, CNIM specialists precisely align the suspended beam and the massive supporting pillars—an operation that can only be performed manually.
Part of Korea's contribution to ITER, the tools are assembled by French contractor CNIM. Lessons learned from SSAT-1 have reduced assembly time for SSAT-2 by approximately one-third.

On Wednesday 9 January, installation operations began for some of the last elements: two 12-tonne beams that stabilize the massive pillars of the machine.

Click here to watch a video of the installation.



return to the latest published articles