Subscribe options

Select your newsletters:

Please enter your email address:

@

Your email address will only be used for the purpose of sending you the ITER Organization publication(s) that you have requested. ITER Organization will not transfer your email address or other personal data to any other party or use it for commercial purposes.

If you change your mind, you can easily unsubscribe by clicking the unsubscribe option at the bottom of an email you've received from ITER Organization.

For more information, see our Privacy policy.

News & Media

Latest ITER Newsline

  • Vacuum components | Shake, rattle, and... qualify!

    A public-private testing partnership certified that ITER's vacuum components can withstand major seismic events. Making sure the ITER tokamak will be safe in th [...]

    Read more

  • Feeders | Delivering the essentials

    Like a circle of giant syringes all pointing inward, the feeders transport and deliver the essentials to the 10,000-tonne ITER magnet system—that is, electrical [...]

    Read more

  • Image of the week | It's FAB season

    It's FAB season at ITER. Like every year since 2008, the Financial Audit Board (FAB) will proceed with a meticulous audit of the project's finances, siftin [...]

    Read more

  • Disruption mitigation | Final design review is a major step forward

    The generations of physicists, engineers, technicians and other specialists who have worked in nuclear fusion share a common goal, dedication and responsibility [...]

    Read more

  • Image of the week | Like grasping a bowl of cereal

    Contrary to the vast majority of ITER machine components, the modules that form the central solenoid cannot be lifted by way of hooks and attachments. The 110-t [...]

    Read more

Of Interest

See archived entries

Cryoplant

A vertical displacement event

Three vertical storage tanks have been installed since last week outside of the cryoplant. The operation requires two powerful cranes working in tandem but also the strength of many arms ...

Installed vertically because of space constraints, six identical tanks will store 380 cubic metres of gaseous helium each at a pressure of 22 bars. (Click to view larger version...)
Installed vertically because of space constraints, six identical tanks will store 380 cubic metres of gaseous helium each at a pressure of 22 bars.
There are 36 semicircular openings at the base of each tank, corresponding to 36 steel rods deeply anchored into the 2.5-metre thick concrete platforms that have been built to receive them. Each tank stands 20 metres high and weighs 150 tonnes.

As the crawler crane seize a tank by its "ears" (two cylindrical protrusions called "trunnions" located at the upper end of the component), and as the telescopic crane slowly lifts its lower end, one wonders how the required alignment will be achieved.

One hour later, the question can be answered. The crawler crane positions the tank vertically and leaves it hovering a few centimetres above the rods. Three men weigh in with all their strength on the bottom rim: a few pushes to the right, a few pulls to the left, a tilt inward and a small rotational movement and everything falls into alignment. The crane operator can then carefully lower the tank so that all 36 rods slide into their corresponding holes, ready to be bolted.

Last Wednesday's operation was a spectacular first. By the end of the week it was routine and as of today's Newsline, three tanks are in place.

Installed vertically because of space constraints, the six tanks, procured by Europe, will each store 380 cubic metres of gaseous helium at a pressure of 22 bars. They will act as buffers for certain phases of operations and also as storage when ITER is not running.

Read a full report on the European Domestic Agency website.


return to the latest published articles