Subscribe options

Select your newsletters:

Please enter your email address:

@

Your email address will only be used for the purpose of sending you the ITER Organization publication(s) that you have requested. ITER Organization will not transfer your email address or other personal data to any other party or use it for commercial purposes.

If you change your mind, you can easily unsubscribe by clicking the unsubscribe option at the bottom of an email you've received from ITER Organization.

For more information, see our Privacy policy.

News & Media

Latest ITER Newsline

  • Image of the week | The platform's quasi-final appearance

    Since preparation work began in 2007 on the stretch of land that was to host the 42-hectare ITER platform, regular photographic surveys have been organized to d [...]

    Read more

  • Cryopumps | Preparing for the cold tests

    Before being delivered to ITER, the torus and cryostat cryopumps are submitted to a  comprehensive series of factory acceptance tests. This is not sufficie [...]

    Read more

  • Fusion technologies | Closing a fusion schism

    Historically, inertial confinement and magnetic confinement approaches to fusion have been parallel, separate processes. The ITER Private Sector Fusion Workshop [...]

    Read more

  • Toroidal field coil celebration | "A good day for the world"

    A little before 2:00 a.m. on 17 April 2020 a powerful transport trailer, accompanied by dozens of technical and security vehicles, passed the gates of the I [...]

    Read more

  • Press conference | New baseline to prioritize robust start to exploitation

    At a press conference on 3 July attended by approximately 200 journalists and key ITER stakeholders, ITER Director-General Pietro Barabaschi answered questions [...]

    Read more

Of Interest

See archived entries

Load tests

Lifting and moving four Boeing 747s

It's almost midnight and everything is still on the ITER worksite. Everything? Not quite. In the Assembly Hall, a small group of people are craning their necks to carefully monitor the nearly imperceptible movements of a large mass of steel suspended some 50 metres above the floor.

High in the rafters, the trolley's electrical motors are pulling with all their strength at the cables holding the dummy load, 10 percent heavier than the nominal lifting capacity (1,500 tonnes) of the massive double overhead crane. (Click to view larger version...)
High in the rafters, the trolley's electrical motors are pulling with all their strength at the cables holding the dummy load, 10 percent heavier than the nominal lifting capacity (1,500 tonnes) of the massive double overhead crane.
High in the rafters, electrical motors are whirring, pulling with all their strength at the thick cables that hold the 1,650-tonne load—the equivalent of 1,500 average-sized cars, 300 African elephants or five fully loaded Boeing 747s.

The date is 18 December and this is the second-to-last of the "load tests" for the main cranes in the Assembly Hall.

A few days earlier, in order to prove the resistance of the crane's structural elements, the slings had been put into tension with an even heavier load (1,875 tonnes). These "static" tests had confirmed that the double overhead crane could withstand, without difficulty, a load 25 percent heavier than the nominal lifting capacity of 1,500 tonnes.

Now, with a load 10 percent heavier than nominal, the crane system is being tested "dynamically," performing all the movements that will be required for the handling of the actual machine components. What needs to be observed and measured this time is the building's "behaviour."

Dynamic tests cover all the movements that will be required for the handling of the actual machine components. What they aim to measure are the transient millimetric deformations of the building's steel structure. (Click to view larger version...)
Dynamic tests cover all the movements that will be required for the handling of the actual machine components. What they aim to measure are the transient millimetric deformations of the building's steel structure.
As the load slowly moves along the width of the Assembly Hall—and then along its length—the building's structure is submitted to considerable forces, causing the steel pillars of its frame to compress and flex.

The building is designed to accommodate these transient millimetric deformations that laser measurements closely monitor. "The steel structure is elastic," explains a surveyor from the architect-engineer Engage. "We know precisely, from computer models, what the expected values are. We're just making sure that what we are observing tonight remains within the anticipated numbers."

One last test needs to be performed before the crane system can be fully commissioned. Called the "DCHLB test," for Dual Crane Heavy Lifting Beam, it will consist in attaching the four crane hooks to a single connection point in the form of a massive clevis.

Such a configuration is required to interface with the dedicated tools that will lift vacuum vessel sectors and the central solenoid.

Load tests are performed at night, when no activity is ongoing in the Assembly Hall. Participants include specialists from the crane manufacturer Reel, the ITER Organization, the architect-engineer Engage and the safety controller Bureau Veritas. (Click to view larger version...)
Load tests are performed at night, when no activity is ongoing in the Assembly Hall. Participants include specialists from the crane manufacturer Reel, the ITER Organization, the architect-engineer Engage and the safety controller Bureau Veritas.
In about a year, the crane system in the Assembly Hall will begin handling actual machine components—massive steel pieces (or pre-assemblies) that will be delicately moved and deposited inside the "well" formed by the bioshield to be assembled and integrated. Like a giant hand performing a watchmaker's job.



return to the latest published articles