Subscribe options

Select your newsletters:

Please enter your email address:

@

Your email address will only be used for the purpose of sending you the ITER Organization publication(s) that you have requested. ITER Organization will not transfer your email address or other personal data to any other party or use it for commercial purposes.

If you change your mind, you can easily unsubscribe by clicking the unsubscribe option at the bottom of an email you've received from ITER Organization.

For more information, see our Privacy policy.

News & Media

Latest ITER Newsline

  • Vacuum vessel repair | A portfolio

    Whether standing vertically in the Assembly Hall or lying horizontally in the former Cryostat Workshop now assigned to component repair operations, the non-conf [...]

    Read more

  • European Physical Society | ITER presents its new plans

    The new ITER baseline and its associated research plan were presented last week at the 50th annual conference of the European Physical Society Plasma Physics Di [...]

    Read more

  • Image of the week | The platform's quasi-final appearance

    Since preparation work began in 2007 on the stretch of land that was to host the 42-hectare ITER platform, regular photographic surveys have been organized to d [...]

    Read more

  • Cryopumps | Preparing for the cold tests

    Before being delivered to ITER, the torus and cryostat cryopumps are submitted to a  comprehensive series of factory acceptance tests. This is not sufficie [...]

    Read more

  • Fusion technologies | Closing a fusion schism

    Historically, inertial confinement and magnetic confinement approaches to fusion have been parallel, separate processes. The ITER Private Sector Fusion Workshop [...]

    Read more

Of Interest

See archived entries

First plant components now in place

A powerful crane and worker dexterity - that's what is needed to precisely position the 87-ton component onto the supports that span the gravel-covered pit. (Click to view larger version...)
A powerful crane and worker dexterity - that's what is needed to precisely position the 87-ton component onto the supports that span the gravel-covered pit.
The four US-procured transformers that will be needed to distribute power to the ITER installation have all reached the ITER site. The first one had been the first Highly Exceptional Load to travel along the ITER Itinerary in January; three more were delivered on 21 May in a single transport operation.

A mere two hours after arrival, one of the four transformers was readied for installation on the platform in the vicinity of the the 400 kV switchyard. A powerful crane was used to position the 87-ton component on its dedicated pad; the same operation was duplicated the following day. Two transformers are now place—the first installed components of the ITER plant.

The pad onto which each transformer is solidly anchored covers a 1.5-metre-deep, gravel-covered pit that has been dimensioned to receive the 44 cubic metres of oil the component contains (oil is used as an insulator) in case of a leak. Eight-metre walls stand between the pads to prevent a possible fire in one transformer from spreading to the others.

The four transformers will bring down the voltage from 400 kV to the standard 20 kV of industrial installations. "ITER could operate with only three transformers but for reasons of flexibility and redundancy, we have opted for four," explains ITER Electrical Power Distribution section leader Joël Hourtoule.

The second pair of transformers will be installed in the coming weeks.

View a slide show of the convoy and transformer installation below.


return to the latest published articles