Since this picture was taken, on Thursday 23 January, the lattice being constructed to close up the end of the crane hall structure has almost reached the top; it should be completed by 1 February. A first layer of cladding now covers one side of the structure, and 15 percent of insulation and final cladding is now affixed to the beams. Roofing is nearly half in place, and the rails for the over
head cranes are in position on both sides of the hall.
Next time we train the camera on the crane hall, the view will have changed again. And despite all our efforts, the photograph will probably be a few hours late...