One year later, what was once a vast and shiny expanse has turned into an overcrowded cavern. Sheets of protective plywood cover the stainless steel lining of the floor and lower walls; light is scarce and focused on working areas.
In order to install and weld the final anchorage system, the tanks—more than 6 metres tall and weighing up to 180 tonnes— have been lifted some 30 centimetres by way of hydraulic jacks. In this position, standing very close together, the tanks nearly reach the concrete roof two levels above.
Welded on the embedded plates, the anchorage system (bolts, seal lids and shear pins for withstanding lateral seismic accelerations) must be absolutely leak-tight. Non-destructive tests are performed on each individual weld, including a leak tightness performed using a vacuum box specifically designed and customized to fit the geometry under the skirts of the tanks. There are 280 welds, amounting to a total weld length in excess of 400 metres.