At CNIM, like at SIMIC, the manufacturing process is long and painstaking. From the pre-machining of the rough shapes, it takes close to 150 days before a radial plate is finalized and ready to be sent to
ASG Superconductors SpA, in La Spezia, Italy, where the conductor lengths will be inserted. Seven radial plates are needed for the assembly of each toroidal field coil.
"Another main challenge is the tight schedule," explains the CNIM management. "The expected delivery rate is one radial plate every four weeks. To achieve this, our teams must work around the clock in three 8-hour shifts."