Pour les actualités en français, voir la page News in French.

Image of the week

2nd vacuum vessel sector passes site tests

On 27 August, the ITER community celebrated the safe arrival of vacuum vessel sector #1(7)—the second of four sectors expected from the Korean Domestic Agency.
VVS1_Unpacked_1_small.jpg
Since then, the 440-tonne sector has undergone the same early set of activities as its predecessor, sector #6. All site acceptance tests have been passed successfully and metrology is underway to verify the as-built dimensions of the component. 

Sector #1(7) must also be equipped with diagnostics and instrumentation before it can be raised to vertical and installed on the second of two tall assembly tools to be paired with a toroidal field coil pair and thermal shielding.

That operation is on full display now for sector #6, with 13 of 27 milestones achieved (48 percent) on the road to lowering the first vacuum vessel sub-assembly into the Tokamak pit.

An operation that will be repeated nine times in the coming years.