"In a way we were lucky," Tom Painter says retrospectively, "as the rules for this relocation procedure are extremely strict and could easily have meant a few months delay for the project." The rules state that if the weather forecast predicts an overnight temperature below 52 °F (around 11 °C) on any of the three nights following the start of digging, the operation has to be stopped and construction put off. "Since we were already late in the fall, there were many windows when this could have been the case," recalls Tom. In the end, it all worked out fine: the turtles were moved to their new home and the construction of the jacketing facility that runs parallel to the runway continued. By now the facilities are all in place and within the next three-four months commissioning will be terminated.
The buildings at both ends of the jacketing line very much resemble aircraft hangars, which is no coincidence, as Tom Painter's business partner and the co-founder of High Performance Magnetics Richard Benham, explains. "Ideally we will continue to use these facilities for a number of years if there are other jacketing projects that require the use of a similar long footprint. But with an eye towards sustainable development, we chose to design the buildings as aircraft hangars so they could be repurposed without any loss."
Richard Benham has been an entrepreneur for more than 20 years and involved in many startups. "When my friend Tom described the ITER Project to me and the possibility of successfully developing fusion energy, it sounded very attractive. I thought that it was an extremely useful thing to work towards, so I supported Tom to get the business going."