Subscribe options

Select your newsletters:

Please enter your email address:

@

Your email address will only be used for the purpose of sending you the ITER Organization publication(s) that you have requested. ITER Organization will not transfer your email address or other personal data to any other party or use it for commercial purposes.

If you change your mind, you can easily unsubscribe by clicking the unsubscribe option at the bottom of an email you've received from ITER Organization.

For more information, see our Privacy policy.

News & Media

Latest ITER Newsline

  • Poloidal field magnets | The last ring

    As the massive ring-shaped coil inched its way from the Poloidal Field Coils Winding Facility, where it was manufactured, to the storage facility nearby where i [...]

    Read more

  • Heat rejection | White "smoke" brings good news

    Like a plume of white smoke rising from a cardinals' conclave to announce the election of a new pope, the tenuous vapour coming from one of the ITER cooling cel [...]

    Read more

  • WEC 2024 | Energy on centre stage

    The global players in the energy sector convened in Rotterdam last week for the 26th edition of the World Energy Congress (WEC). The venue was well chosen, wit [...]

    Read more

  • Fusion world | The EU blueprint for fusion energy

    The EU Blueprint for Fusion Energy workshop, convened by the European Commission's Directorate-General for Energy, brought together key stakeholders in the fiel [...]

    Read more

  • Neutral beam injection | ELISE achieves target values for ITER

    Researchers at the Max Planck Institute for Plasma Physics in Garching, Germany, have generated the ion current densities required for ITER neutral beam injecti [...]

    Read more

Of Interest

See archived entries

Image of the week

The lighthouse in the pit

Like a lighthouse (without a beacon) the central column rises more than 20 metres above the floor of the assembly pit. The massive structure does not belong to the tokamak, however: once connected to an array of nine radial beams it will form the backbone of a 600-tonne temporary tool that will support, align, and stabilize the vacuum vessel sub-assemblies as they are joined and welded. The tool is designed to support a total nominal weight of 5,400 tonnes.

The central column rises more than 20 metres above the floor of the assembly pit. It is one of the most massive tools used in the assembly process. (Click to view larger version...)
The central column rises more than 20 metres above the floor of the assembly pit. It is one of the most massive tools used in the assembly process.
On 27 March 2021, the first and sturdiest segment of the central column (the 70-tonne bottom cylinder) was lowered into the assembly pit and carefully inserted into the circular opening at the bottom of the cryostat base. Metrology confirmed that the structure was placed within 2 millimetres of its nominal position inside of the Tokamak Global Coordinate System (TGCS).

Five months later, on 20 August, the remaining four sections were successively installed and assembled, bringing the column to its full height.

Each of the nine radial beams will be supported by the central column on one side and the concrete bioshield on the other through brackets embedded in the L2 level of the bioshield wall. On 30 August, the first of these brackets, called a radial beam support, was successfully installed in port cell #12.

The port cells are numbered at the top of the assembly pit (photo). Once all nine vacuum vessel sub-assemblies are in place, the central column will be removed. In its place, operators will install the central solenoid. (Click to view larger version...)
The port cells are numbered at the top of the assembly pit (photo). Once all nine vacuum vessel sub-assemblies are in place, the central column will be removed. In its place, operators will install the central solenoid.
Everything is in place for a first "insertion" test. Later this week, the overhead cranes will lift a test radial beam (without its load) and insert it into the Tokamak pit in order to confirm the alignment between the central column and the radial beam support. This is one of the 27 steps leading to the installation of the first 1,200-tonne vacuum vessel sub-assembly, planned for late October.

 



return to the latest published articles