Subscribe options

Select your newsletters:

Please enter your email address:

@

Your email address will only be used for the purpose of sending you the ITER Organization publication(s) that you have requested. ITER Organization will not transfer your email address or other personal data to any other party or use it for commercial purposes.

If you change your mind, you can easily unsubscribe by clicking the unsubscribe option at the bottom of an email you've received from ITER Organization.

For more information, see our Privacy policy.

News & Media

Latest ITER Newsline

  • Vacuum vessel repair | A portfolio

    Whether standing vertically in the Assembly Hall or lying horizontally in the former Cryostat Workshop now assigned to component repair operations, the non-conf [...]

    Read more

  • European Physical Society | ITER presents its new plans

    The new ITER baseline and its associated research plan were presented last week at the 50th annual conference of the European Physical Society Plasma Physics Di [...]

    Read more

  • Image of the week | The platform's quasi-final appearance

    Since preparation work began in 2007 on the stretch of land that was to host the 42-hectare ITER platform, regular photographic surveys have been organized to d [...]

    Read more

  • Cryopumps | Preparing for the cold tests

    Before being delivered to ITER, the torus and cryostat cryopumps are submitted to a  comprehensive series of factory acceptance tests. This is not sufficie [...]

    Read more

  • Fusion technologies | Closing a fusion schism

    Historically, inertial confinement and magnetic confinement approaches to fusion have been parallel, separate processes. The ITER Private Sector Fusion Workshop [...]

    Read more

Of Interest

See archived entries

Coil winding facility

Gantry crane passes load tests

However complex the science or sophisticated the technology at ITER, there is one simple activity that conditions future success—the ability to lift and manoeuvre exceptionally heavy loads during the project assembly phase.

A 540-tonne load, representing 125 percent of the crane's nominal lifting capacity, is attached to the beams for static tests. Dynamic operations followed at 110 percent in order to monitor the deformation of the beams. (Click to view larger version...)
A 540-tonne load, representing 125 percent of the crane's nominal lifting capacity, is attached to the beams for static tests. Dynamic operations followed at 110 percent in order to monitor the deformation of the beams.
With a nominal lifting capacity of 1,500 tonnes, the undisputed champion of ITER weightlifters is the double overhead crane in the Assembly Hall. Second on the podium is the gantry crane in the Poloidal Field Coils Winding Facility—a 30-metre-in-diameter steel structure supported by four hydraulic towers traveling on rails, capable of lifting the heaviest components of the ring-shaped coils throughout the last stages of fabrication.

Personnel from the European Domestic Agency and from crane manufacturer Ale Heavy Lift are overseeing the load tests. Europe is responsible for procuring 5 out of the 6 poloidal field coils required for ITER operation. (Click to view larger version...)
Personnel from the European Domestic Agency and from crane manufacturer Ale Heavy Lift are overseeing the load tests. Europe is responsible for procuring 5 out of the 6 poloidal field coils required for ITER operation.
Load tests for the gantry crane began on 16 February with static operations at 125 percent of its nominal lifting capacity of 400 tonnes. Dynamic operations followed at 110 percent in order to monitor the deformation of the beams. With a deflection of less than 119 millimetres, the tests were conclusive.

The bright red gantry crane was tested in three operational lifting configurations corresponding to poloidal field coils #2 and #5 (up to 342 tonnes, Ø 17 metres), poloidal field coils #3 and #4 (up to 385 tonnes, Ø 24 metres), and finally poloidal field coil #6 (396 tonnes, Ø 8.5 metres)¹.

¹ Poloidal field coil #6 (PF6) is being manufactured in China under a European contract but will be cold tested in the on-site poloidal field coil facility.
 
For more on the poloidal field coils click here and here.


return to the latest published articles