Your email address will only be used for the purpose of sending you the ITER Organization publication(s) that you have requested. ITER Organization will not transfer your email address or other personal data to any other party or use it for commercial purposes.
If you change your mind, you can easily unsubscribe by clicking the unsubscribe option at the bottom of an email you've received from ITER Organization.
Image of the Week | Hard work deserves an outdoor buffet
A start-of-summer event was held on Friday 21 June for the ITER community—an occasion to celebrate the everyday commitment of staff and contractors alike, acros [...]
Poloidal field coils | Reflecting on a unique industrial achievement
They had worked together for 10 years. And on Thursday 20 June, they gathered one last time to reflect on what they had accomplished. Director-General Pietro Ba [...]
Nearly 100 people met for two days last week for the 34th Meeting of the ITER Council. The meeting was an important one, as the ITER Organization and the D [...]
The ITER vacuum team, the European Domestic Agency Fusion for Energy, Research Instruments (RI), and the ITER Director-General were all excited to welcome the d [...]
Tritium Plant Summit | A shared vision to prepare for delivery
A summit organized at ITER Headquarters from 3 to 6 June brought together the international teams that will deliver the sub-systems of the ITER Tritium Plant. I [...]
The main elements of the 1,500-tonne double overhead bridge crane—four girders and their corresponding trolleys—are now in place in the Assembly Hall. The big red crawler crane has been dismantled and is on its way to Sweden, where a 330-tonne "sphere" for liquid gas storage is waiting for a lift.
The most spectacular part of the operation is over. However, a considerable amount of work remains to be done, most of it at height, to finalize cabling connections, platform and walkway fittings, and the like--the "finishing" activities of the bridge crane installation.
By late September or early October, the two auxiliary cranes, each with a lifting capacity of 50 metric tonnes, will be delivered and installed. This time, there will be no need for a monster crawler crane operating from outside the building ...
Preliminary testing and commissioning are scheduled to begin in January/February 2017 for the large crane, and a few months later for the smaller one.